Oman’s Al Dakhiliyah Advances OMR103 Million in Road and Infrastructure Works

By Mehdi Touzene · 2026-11-10 10:53 UTC

Road and infrastructure projects worth more than OMR103 million are under way across Al Dakhiliyah. The works aim to improve access between homes, services and tourism destinations, with several major roads still in progress.

Al Dakhiliyah is advancing road and infrastructure works worth more than OMR103 million, bringing the prospect of easier journeys between residential communities, service centres and tourism destinations. The programme spans local streets and larger routes across the governorate, with projects at different stages of construction.

What is under way

According to Times of Oman, works undertaken by Al Dakhiliyah Governorate across its wilayats exceed OMR22.2 million. Projects implemented by the Ministry of Transport, Communications and Information Technology are valued at approximately OMR81.6 million. Together, they cover internal roads, dualisation of main routes, mountain-road improvements, maintenance, road protection and valley drainage.

Sheikh Hilal bin Saeed Al Hajri, Governor of Al Dakhiliyah, said road development is central to improving access to services and linking wilayats with residential communities. He said priorities reflect population needs and development requirements in each wilayat, while coordination with ministry projects is intended to make better use of infrastructure investment.

Progress across the governorate

In Nizwa, internal-road packages covering 44 kilometres had reached 87% and 79% completion by the end of September. An additional exit and parking facilities at Nizwa Central Market were 33% complete. In Bahla, work on 18 kilometres of internal roads had reached 99% on some sections and 50% on others.

Other local works include 19 kilometres of roads in Al Hamra at 91% completion, 20 kilometres in parts of Izki at around 70%, and the first 13-kilometre phase of internal roads in Samail at 40%. The governorate has also recently signed contracts worth more than OMR5.7 million for road maintenance and new connections serving residential communities and areas of urban expansion.

Among the ministry’s larger projects, dualisation of the Izki–Nizwa Road had reached 36% completion and is scheduled to finish in March 2028. The 32-kilometre Jabal Shams Road project was 9.3% complete, with completion expected in January 2028. Work to upgrade the 9.1-kilometre Saih Qatna Road in Al Jabal Al Akhdar had reached 75%.

What it means for buyers and investors

For someone considering property in Al Dakhiliyah, better roads may make a location more practical by improving everyday access to services and travel between communities. Routes serving tourism destinations may also be relevant to buyers assessing how easily a property can be reached. These are potential benefits to assess, not a forecast of property demand or values.

The key consideration is timing: completion varies considerably by project, and work on a nearby road does not mean the whole journey has improved. Buyers can compare a property’s location with the specific routes being upgraded and watch for construction progress, drainage improvements and announced completion milestones before relying on future access in a purchase decision.

Source: Times of Oman.